<p>AN ordinance concerning business.
<p>AN ordinance concerning business.
Be it enacted by the [Insert Governing Body],represented in the [Insert Jurisdiction]:
Be it enacted by the [Insert Governing Body], represented in the [Insert Jurisdiction]:
Section 1. The Contractor Prompt Payment Ordinance as follows:
Section 1. The Contractor Prompt Payment Ordinance as follows:
A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held. After the contract is 50% complete, no more than 5% of the amount of any subsequent payments made under the contract may be held as retainage.</p>
A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held. After the contract is 50% complete, no more than 5% of the amount of any subsequent payments made under the contract may be held as retainage.</p>

Latest revision as of 15:40, 19 April 2021

Model Bill Info
Bill Title Prompt Payment Ordinance
Date Introduced June 16, 2020
Date Finalized August 9, 2020
Type Model Ordinance
Status Final
Task Forces American City County Exchange

Prompt Payment Ordinance

AN ordinance concerning business. Be it enacted by the [Insert Governing Body], represented in the [Insert Jurisdiction]: Section 1. The Contractor Prompt Payment Ordinance as follows: A construction contract may provide for the withholding of retainage of up to 10% of any payment made prior to the completion of 50% of the contract. When a contract is 50% complete, retainage withheld shall be reduced so that no more than 5% is held. After the contract is 50% complete, no more than 5% of the amount of any subsequent payments made under the contract may be held as retainage.